(a) Any owner seeking to construct a new, or to modify an existing electric power subtransmission line shall submit a report to the Department and to the Mayor of each township to be affected at least 90 days prior to the planned start of construction or modification. The information will be used for a database and shall be a public record. This report shall contain the following information:
1. The highest operating voltage.
2. The anticipated average and maximum current flow per phase and normal flow direction.
3. Physical dimensions of and between all conductors and distance of conductors to earth.
4. A route map based on the New Jersey Plane Coordinate system or latitude and longitude and standardized geographic coordinates of all structure locations in digital form.
5. Calculated values of the magnetic fields under anticipated average and maximum current flow conditions at every 25 foot interval from the centerline, as measured perpendicular thereto, to the edge of the ROW or 100 feet from the centerline, whichever is greater, in accordance with 7:28-44.6 (Computational Methodology).
6. Date of anticipated energization.